Phil Easom






[Picture]
Architect J,W. Hodges, Generation development and
construction division, CEGB.


Quantity surveyors Inman & Partners.

Electrical, heaters and
ventilating consultants


EDC London.
Main contractor Thomas Lowe & Sons, Burton-upon-Trent,
Staffs.


Electrical sub-contractor Drake & Skull Ltd.

Construction Steel frame erected by Stephensons, Norwich.

Heating and ventilating Electric warm air system by Woods of Colchester.

Heating and ventilating controls         Drayton Controls Ltd.

Electrical switchgear MEM Electrical Ltd.

Overhead crane Alien & Co. Ltd.

Compressed air services Broom & Wade, High Wycornbe.

Total area 3,132 Sq. Metres

Total electrical load 1.2 MW

Total cost £345,000

[Picture]
Checking for a fault in
an amplifier - the total
value of the plant
training centre's
equipment is nearly
£140,000.


Cost of building £268,000

Cost of equipment £77,000

Additional equipment Scrap, redundant and unserviceable items
acquired from power stations.
Estimated value £60,000.
[Picture]
[Picture]